Burlington Docket
Passed on the consent agenda

Council approves $1,326,385 contract for new water mains on Pine and Summit

Official title: Construction Contract for 2026 Water Distribution Improvements - DPW - Water Resources

Public Works Department - Water ResourcesSince May 11, 2026
In plain English

The council authorized Public Works to sign a $1,326,385 contract with S.D. Ireland Brothers Corporation to replace about 2,500 feet of water pipe on Pine Street, Summit Street and Bennington Court. It also allowed up to $265,277 more in contingency funding. The streets have had repeated water main breaks.

Where it stands
  1. IntroducedMay 11
  2. Board of Finance
  3. PassedMay 18

The council approved the contract on May 18, 2026 as part of its consent agenda.

Quick answers
Where is this?

Pine Street from Home Avenue south to the Champlain Parkway project limits, Summit Street between Main Street and Maple Street, and Bennington Court.

What does it cost?

The contract is $1,326,385, with up to $265,277 in contingency, for a total of $1,591,662. It is paid from a state revolving fund loan and the 2025 water bond, and the memo estimates debt payments of about $78,918 a year.

When does it take effect?

Bennington Court must be finished by July 31, 2026. Pine and Summit Streets must be built within 270 days and could finish in spring 2027 after a winter pause.

History
  1. May 182026
  2. May 112026
Documents

Related