Public Works seeks $2,033,000 water and $2,604,600 sewer loans for Cherry Street

Official title: Cherry Street Water Distribution Improvements, Step III DWSRF Loan Application & Cherry Street Sewer Collection Improvements, Step III CWSRF Loan Amendment - DPW - Water Resources

Public Works Department - Water ResourcesSince Jun 15, 2026
Speak on this
In plain English

Public Works asked the Board of Finance to recommend applying for a $2,033,000 drinking water loan and a $2,604,600 sewer loan amendment for the Cherry Street rebuild. The work includes about 1,400 feet of water main replacement and about 2,100 feet of sewer pipe replacement and upsizing.

Where it stands
  1. IntroducedJun 15
  2. Board of Finance
  3. Council vote

The Board of Finance had it on June 15, 2026, and the record shows no decision. The memo lists a City Council date of June 29, 2026.

Quick answers
Where is this?

Along Cherry Street, as part of the Great Streets project that also covers Pine and St Paul Streets, with Bank Street likely a later phase.

What does it cost?

Up to $2,033,000 for water and $2,604,600 for sewer. The memo says the water loan has up to a 1% interest rate and up to a 2% administrative fee, repaid over up to 30 years. It says the sewer loan has a 2% annual administrative fee instead of interest and a 20 to 30 year term.

When does it take effect?

The memo says bids would be advertised in early 2027, opened in spring 2027, and construction would start in summer 2027.

History
  1. Jun 152026