Public Works seeks $2,033,000 water and $2,604,600 sewer loans for Cherry Street
Official title: Cherry Street Water Distribution Improvements, Step III DWSRF Loan Application & Cherry Street Sewer Collection Improvements, Step III CWSRF Loan Amendment - DPW - Water Resources
Public Works asked the Board of Finance to recommend applying for a $2,033,000 drinking water loan and a $2,604,600 sewer loan amendment for the Cherry Street rebuild. The work includes about 1,400 feet of water main replacement and about 2,100 feet of sewer pipe replacement and upsizing.
- IntroducedJun 15
- Board of Finance
- Council vote
The Board of Finance had it on June 15, 2026, and the record shows no decision. The memo lists a City Council date of June 29, 2026.
Where is this?
Along Cherry Street, as part of the Great Streets project that also covers Pine and St Paul Streets, with Bank Street likely a later phase.
What does it cost?
Up to $2,033,000 for water and $2,604,600 for sewer. The memo says the water loan has up to a 1% interest rate and up to a 2% administrative fee, repaid over up to 30 years. It says the sewer loan has a 2% annual administrative fee instead of interest and a 20 to 30 year term.
When does it take effect?
The memo says bids would be advertised in early 2027, opened in spring 2027, and construction would start in summer 2027.
- Jun 152026
- PDFBOF-CC Memo Cherry St. DWSRF & CWSRF Loan Application & Amendment685 KB
- PDF2026.06.15 WR Resolution re Attachment A - Resolution W Step III DWSRF Amendment 6-202672 KB
- PDF2026.06.15 WR Resolution re Attachment A - Supp Bond Res No. 7 - Wtr Sys Rev Bonds141 KB
- PDF2026.06.15 WR Resolution re Attachment B - Resolution WW Step III CWSRF Amendment 6-202674 KB
- PDFBOF-CC Checklist - Cherry St. DWSRF & CWSRF Loan Application & Amendment516 KB
Related
- PassedStreets & transit
Council approves $1,326,385 contract for new water mains on Pine and Summit
- PassedEnvironment & energy
Council takes up $1,790,700 state loan for Manhattan Drive stormwater repairs
- PassedEnvironment & energy
Council authorizes up to $2,604,600 state loan for Cherry Street sewer upgrade
- On the agendaMoney & taxes
Distribution and Collection System Improvements - Contractor Budget Amendment - DPW - Water Resources
- On the agendaStreets & transit
Great Streets Main Street - Sewer Budget
- PassedStreets & transit
Authorization For Up To $518,600 Step II Loan From Vermont Clean Water State Revolving Fund, For An Engineering Contract With Wright Pierce For Up To $70,000 And For An Amended Engineering Contract With Stantec For An Additional Amount Up To $50,000 For The Upsized Sewer On Cherry Street Project
- On the agendaEnvironment & energy
Council authorizes $544,000 state loan for water distribution and storage planning
- PassedMoney & taxes
Council OKs up to $558,500 from water fund for treatment plant planning