Council approves Cherry Street easement decisions, with no votes against
Official title: Reconnecting Bank & Cherry (Cherry Street), CDS CD23(1), Decisions on Condemnation Proceedings
Public Works asked the council, sitting with the mayor presiding, to let the mayor sign two written decisions on taking easements over the Cathedral of the Immaculate Conception trust property at 20 Pine Street for the Cherry Street rebuild. The council approved the decision on necessity 9 to 0 with two abstentions, and the decision on compensation 7 to 0 with five abstentions.
- IntroducedJul 13
- PassedJul 13
Both decisions were approved on July 13, 2026. The documents note a September 30, 2026 federal construction funding deadline for securing property rights.
Who does this affect?
The owner of 20 Pine Street, the Cathedral of Immaculate Conception Parish Charitable Trust, which gets temporary and permanent easements for sidewalk and catch basin work. Its attorney argued a two-thirds voter approval was needed, and the city said it was proceeding as a highway alteration.
What does it cost?
The documents do not give a compensation amount for the easements. The wider project has a $12 million congressionally directed grant for Cherry Street and a $22 million federal RAISE grant for the whole project area.
When does it take effect?
The easements follow the July 13, 2026 votes, after City Attorney review. The project has a September 30, 2026 federal deadline to secure all property rights.
- Jul 132026
Related
- PassedStreets & transit
Council closes Cherry Street easement hearing; city offers church trust $6,850
- On the agendaStreets & transit
Council holds hearing on easements for Cherry Street rebuild, one owner still objects
- ReceivedStreets & transit
Public Works proposes splitting Bank and Cherry rebuild to close a $16.6 million gap
- Passed unanimouslyStreets & transit
Council OKs land takings for Colchester and Riverside Avenue intersection work
- On the agendaStreets & transit
Cherry Street Condemnation Request: Reconnecting Bank and Cherry Streets
- PassedStreets & transit
Council authorizes up to $2,033,000 state loan for Cherry Street water main work
- PassedEnvironment & energy
Council authorizes up to $2,604,600 state loan for Cherry Street sewer upgrade
- In committeeStreets & transit
Public Works seeks $2,033,000 water and $2,604,600 sewer loans for Cherry Street