Public Works proposes splitting Bank and Cherry rebuild to close a $16.6 million gap
Official title: Reconnecting Bank & Cherry Project Update
Public Works told the council the Bank Street and Cherry Street rebuild is estimated at about $48 million against $31,395,000 in grants, a shortfall of about $16.6 million. It proposes building Cherry, St. Paul and Pine streets first and moving Bank Street to a later phase, which would cut the shortfall to about $1.2 million.
- IntroducedDec 15, 2025
- Council vote
The report was on the Jan. 12 consent agenda with a recommended action to accept it and place it in the file. The minutes in the record record no vote.
Who does this affect?
Downtown businesses, residents and drivers near Cherry, Bank, St. Paul and Pine streets. The city met with Bank and Cherry Street business owners about limiting construction impacts.
What does it cost?
About $48 million in all, or $32,655,582 without Bank Street. Grants cover $31,395,000. The documents say the remaining $1.2 million could be closed with design savings and smaller grants.
When does it take effect?
The city must meet a construction funding deadline of June 2026 for the $15 million Cherry Street grant. Public Works expects to put the Cherry, St. Paul and Pine work out to bid in late 2026.
- Jan 122026Passed on the consent agendaCity Council · Consent Agenda
- Dec 15, 20252025Presented, no voteCity Council · Deliberative Agenda
Related
- PassedStreets & transit
Council approves Cherry Street easement decisions, with no votes against
- PassedStreets & transit
Council closes Cherry Street easement hearing; city offers church trust $6,850
- On the agendaStreets & transit
Council holds hearing on easements for Cherry Street rebuild, one owner still objects
- Passed 9–3Streets & transit
Council lets public works open Champlain Parkway before signals run 3 months, 9 to 3
- In committeeEnvironment & energy
Wastewater Treatment Plant Improvement Project Update
- On the agendaStreets & transit
Cherry Street Condemnation Request: Reconnecting Bank and Cherry Streets
- ReceivedZoning & building
Work Session Regarding Memorial Block Redevelopment Project Update
- ReceivedHealth & community
BHS/BTC Project Update - Burlington School District