Burlington Docket
Report accepted Jan 12

Public Works proposes splitting Bank and Cherry rebuild to close a $16.6 million gap

Official title: Reconnecting Bank & Cherry Project Update

DPWSince Dec 15, 2025
Speak on this
In plain English

Public Works told the council the Bank Street and Cherry Street rebuild is estimated at about $48 million against $31,395,000 in grants, a shortfall of about $16.6 million. It proposes building Cherry, St. Paul and Pine streets first and moving Bank Street to a later phase, which would cut the shortfall to about $1.2 million.

Where it stands
  1. IntroducedDec 15, 2025
  2. Council vote

The report was on the Jan. 12 consent agenda with a recommended action to accept it and place it in the file. The minutes in the record record no vote.

Quick answers
Who does this affect?

Downtown businesses, residents and drivers near Cherry, Bank, St. Paul and Pine streets. The city met with Bank and Cherry Street business owners about limiting construction impacts.

What does it cost?

About $48 million in all, or $32,655,582 without Bank Street. Grants cover $31,395,000. The documents say the remaining $1.2 million could be closed with design savings and smaller grants.

When does it take effect?

The city must meet a construction funding deadline of June 2026 for the $15 million Cherry Street grant. Public Works expects to put the Cherry, St. Paul and Pine work out to bid in late 2026.