Airport sound insulation: council OKs $4,506,801 contract, raises oversight pay

Official title: Request to execute contracts with Strong Tower Inc. (ST) for the construction improvements to 39 housing units for Bid 1 and Jones Payne Group Inc. (JPG) for the construction oversight services for approximately 58 housing units including Bid 1 and pending Bid 2 of the Airport's Residential Sound Insulation Program (RSIP), funded by the Office of Local Defense Community Cooperation (OLDCC)

AirportSince Jun 15, 2026
In plain English

The airport asked to pay Strong Tower Construction up to $4,506,801 to add sound insulation to 39 homes, and Jones Payne Group to oversee the work on about 58 homes. On September 14 the council raised the Jones Payne amount from $1,151,233 to $1,666,838, plus a 10% contingency. A federal grant funds the program.

Where it stands
  1. IntroducedJun 15
  2. Board of Finance
  3. PassedSep 14

The council authorized the Strong Tower contract on June 29 and the larger Jones Payne amount on September 14, 2026, both on the consent agenda.

Quick answers
Who does this affect?

Owners of homes near the airport in South Burlington, Winooski and Williston that are selected for new windows, doors and ventilation. The memo says about 39 homes in the first round and about 58 after a second bid.

What does it cost?

Strong Tower is authorized up to $4,957,481 including a 10% contingency. Jones Payne is now authorized up to $1,833,521 including contingency, up from $1,266,356. The memo says a $7,320,760 federal grant and an $813,418 local share make up the $8,134,178 total project.

When does it take effect?

The documents do not say. The draft Jones Payne contract runs through December 31, 2030, and the Strong Tower contract term is 224 calendar days from its effective date.

History
  1. Sep 142026
  2. Aug 242026
  3. Jun 292026