Committee reviews Burlington's FY27 regional transportation planning requests

Official title: FY 27 UPWP Public Hearing & Application Approval - Action

Since Jan 27, 2026
Speak on this
In plain English

Public Works staff asked the Transportation, Energy and Utilities Committee to support Burlington's projects in the county planning commission's FY27 work program. New requests are a $96,000 safety audit of the VT 127 corridor and a review of Pearl Street pedestrian signal timing, alongside two ongoing studies.

Where it stands
  1. IntroducedJan 27
  2. Transportation, Energy and Utilities Committee
  3. Council vote

The committee heard the item on January 27 for information and on February 19, 2026 for a vote on supporting the projects; the record does not show the result.

Quick answers
Who does this affect?

People who use the VT 127 corridor, Pearl Street, and Main Street between Winooski Avenue and East Avenue, which are covered by the requests. Colchester and South Burlington support some of the projects.

What does it cost?

The VT 127 audit is estimated at $96,000 with a $16,000 city match that may be waived. The ongoing transportation plan needs $50,000 from Transportation Capital and $10,000 from Penny for Parks; most funding is federal.

When does it take effect?

The work program runs with the city fiscal year. The county planning commission's board is expected to approve the program in May 2026.