Burlington Docket
Passed on the consent agenda

Council approves state grant application to replace Church Street bollards

Official title: 2026 Downtown Transportation Fund Grant Application

Ranjit "Buddy" SinghSince Jan 13, 2026
In plain English

Councilor Singh's resolution lets the Church Street Marketplace apply to the state's FY2026 Downtown Transportation Fund for replacement bollards at five Marketplace intersections. The memo says more than half of the current ones have reached the end of their useful life or been stolen. The project would cost no more than $150,000.

Where it stands
  1. IntroducedJan 13
  2. Planning Commission
  3. PassedJan 20

The council adopted the resolution unanimously on January 20, 2026, after it was moved from the consent agenda to the deliberative agenda.

Quick answers
Who does this affect?

Pedestrians and visitors at the Church Street Marketplace and nearby streets, where the bollards keep vehicles out of the pedestrian-only area.

What does it cost?

The total project cost would not exceed $150,000, with a 20% local match paid from the Marketplace budget, staff time and any donations secured before the application deadline.

When does it take effect?

The council's approval lets the application go forward. The documents do not say when the state will decide or when bollards would be installed.

History
  1. Jan 202026